Trenton Falls Gabion Wall and Lower Access Road Repair |
|
|
Project Outline:

Maintaining high safety and environmental standards while overseeing construction to ensure a quality project within an established budget. Spring high water had washed out the lower access road to the generating station, consequently
Chant’s scope of work included:
- excavating to bedrock
- anchoring foundations for and building a 25’ long x 21’ high concrete deflection wall and 100’ long x 15’ deep x 18’ tall gabion wall
- installing 3,000 square feet of rip rap along 150’ of shoreline
- rebuilding the access road and installing safety barrier
Project Value : |
|
$ 500,000.00
|
| Duration: |
|
2011 (July to October)
|
Chant's Role
|
|
Construction Manager / Contract Manager
|
| Owner: |
|
Brookfield Renewable Power
|
| Contact: |
|
Rick Heysler (315) 896-8551
|
| Contact: |
|
Gerald Westerman (905) 374-5200 |
|