| Project Outline:
The project involves:
- Dewatering of the power canal.
- Debris removal.
- Intake structure concrete demolition.
- Installation of pre-cast panels.
- The removal and installation of new 1 inch trash racks to all four intakes.
| Project Value: |
|
$400,000.00 USD |
| Duration: |
|
October - November 2006 |
| Key Personnel: |
|
Richard McGivern
Anthony Ramirez |
| Owner: |
|
Brookfield Power
New York |
| Reference: |
|
Tom Uncher