Project Outline:

Edworthy ErosionThe project involved the rehabilitation of an existing slope surface and the installation of an earth slope retention system.

Key features of the Project are:

  • Widening of park access road at narrow areas.
  • Removal of grubbed materials and preparation of existing slope surface.
  • Installation of mechanical stabilized earth slope retention system and erosion mat.
  • Hydroseeding of other sloped surfaces.
  • Site restoration.
Tender
Value:
 
$159,700.00
Year:
  2001
Key
Personnel:
 
Dwight Grieve
Owner:   City of Calgary
Owner
Reference:
  Ian Morley
(403) 268-5086
Consultant:   Tensar Earth Technologies Inc.
Contact:   John Kerr
(403) 257-0699

 

 

 