| Project Outline:
This project included the removal of an existing single span concrete steel structure and replacing it with a new 16 m concrete structure.
- Demolition and disposal of existing bridge.
- Construction of new abutments.
- Erection of prestressed beams and concrete deck.
- Widening of all approach roads.
| Tender Value: |
|
$483,000.00 |
| Year: |
|
2000 |
Key Personnel
|
|
Ted Chant |
| Owner: |
|
County of Victoria |
| Consultant: |
|
G. D. Jewell Engineering Inc. |
| Reference
|
|
John Foster
(613)392-0966 |
|