Gordon Street Bridge < Back
   
Project Scope:
  • Erection of a temporary pedestrian bridge.
  • Removal of an existing two-lane bridge.
  • Installation of a new two-lane bridge.
  • Precast arches set on new footings.
  • Granular backfill and pavement placed directly over the arches.
Tender Value:   $1,481,000.00
Year:   2000
Key
Personnel:
  Dwight Grieve
Owner:   City of Guelph
Reference:   Wayne Cheater
(519) 837-5604
Consultant:   Totten Sims Hubicki
Contact:   Ernst Heinrichs
(519) 886-2160

 

 